Internal ERP data migrationActive
INT · Potenz (internal) · Due Nov 15, 2026 · Internal
Progress
0%
0/3 tasks done
Budget used
1%
$506.25 of $45,000.00
Hours logged
13.5
Across the team
Unbilled
$0.00
Non-billable
Tasks
To Do2
Build ETL pipeline
Tomás Guerrero · 44h
Due Oct 5, 2026
Reconciliation checks
Amara Okafor · 20h
Due Oct 20, 2026
In Progress1
Map legacy schema
David Chen · 28h
Due Sep 15, 2026
Done0
No tasks
Milestones
| Schema freeze | Sep 20, 2026 | Upcoming |
Team
| David Chen | Staff Accountant | $37.50/h |
| Tomás Guerrero | Software Engineer | $64.42/h |
| Amara Okafor | Controller | $61.54/h |